AT&S Receives Certification for New IC Substrate Plant in China


Reading time ( words)

Highlights:
  • Certification successfully completed after roughly 17 months of qualification
  • Start of serial production of IC substrates in Q4 of the financial year 2015/16
  • AT&S is thus the first high-end IC substrate manufacturer in China
  • EUR 195.6 million invested in the IC substrate plant by 31.12.2015 – a total of EUR 280 million by the end of the financial year 2016/17
  • Start-up costs will influence results in Q4 2015/16 and beyond

AT&S, one of the global technology leaders for high-end printed circuit boards (PCBs), received the certification for its new plant in Chongqing, China, after roughly 17 months of comprehensive development for the serial production of IC substrates. As a result, serial production will start for the first of two production lines. AT&S will manufacture IC substrates, so-called Flip Chip Ball Grid Array substrates for the use in microprocessors.

Andreas Gerstenmayer, CEO of AT&S, says: “The certification is a milestone for us. In record time, we have established a complex production site and provided a highly sophisticated technology, which was completely new to us, for serial production. We are very proud of this achievement, which would not have been possible without the enormous commitment of our employees and the close cooperation with our initial customer. Now we can start serial production as the first high-end IC substrate manufacturer in China.”

Regarding the strategy that AT&S pursues with this plant, Gerstenmayer says: “We want to continue to grow profitably on the basis of high-end technology in the future. The IC substrate technology will make a significant contribution midterm. In the startup phase we expect negative impacts on the results accordingly.”

After many months during which all equipment and hundreds of process steps were set precisely to the new technology and test substrates were produced under serial production conditions, comprehensive tests for the final certification were carried out in the last months.

The first production line will now be ramped up step by step. Currently, the equipment for the second production line is gradually being installed at the plant and then certified. The second production line is scheduled to start in the third quarter of the financial year 2016/17 (1.10. – 31.12.2016). The two production lines have a capacity of roughly 75,000 sqm/year.

About 1,300 people are currently working at the IC substrate plant in Chongqing; overall the number will total approx. 1,500 for the two lines. So far, EUR 195.6 million has been invested in tangible fixed assets. By the end of the financial year 2016/17, the investment total for the IC substrate plant will add up to roughly EUR 280 million.

The expected cost associated with the start-up of the plant will start to take effect in the fourth business quarter (1.1. – 31.3.2016) and has been taken into account in the guidance for the financial year 2015/16.

What are IC substrates? IC substrates serve as a connection platform between the semiconductor (chips) and PCBs, they “transmit” the nano-structures of the chip onto the PCB (micrometre structures) and are used in microprocessors for computers, communication, automotive and industrial applications. In comparison to PCBs, IC substrates have much finer structures (approx. 40 micrometres vs. approx. 12 micrometres), and different basic materials as well as different production processes are used. Depending on the application, there is a wide variety of substrate technologies with different assemblies and performance requirements.

Fact & figures on AT&S in Chongqing:

  • Total investment of EUR 480 million for two plants by mid-2017:

- Approx. EUR 280 million for two production lines IC substrates (FCBGA substrates)

- Approx. EUR 200 million for two production lines substrate-like PCBs (SLP)

  • Start of first production line IC substrates in Q4 of the financial year 2015/16 (1.1. – 31.3.2016)
  • Start of the second production line IC substrates estimated for Q3 of financial year 2016/17 (1.10. – 31.12.2016)

Share

Print


Suggested Items

iNEMI’s PCB Roadmap Explained

05/01/2020 | Pete Starkey, I-Connect007
In an informative and enlightening webinar, iNEMI Project Manager Steve Payne was joined by Isola Group CTO Ed Kelley to explain, review, and discuss the details of the recently published “iNEMI 2019 Roadmap for Organic PCBs.” Pete Starkey provides an overview.

This Month in PCB007 Magazine: A Scorecard for Suppliers

03/25/2020 | Patty Goldman, I-Connect007
Al Block and Naji Norder from National Instruments talk about the PCQR2 tool, what that entails, and how companies can use the data-driven analysis to validate the quality of suppliers and potentially save millions.

2020 EIPC Winter Conference, Day 2

03/10/2020 | Pete Starkey, I-Connect007
Rested and refreshed, delegates returned to the conference room for the second day of the 2020 EIPC Winter Conference in Blijdorp, Rotterdam, South Holland. Pete Starkey provides an overview of the presentations and activities from Day 2.



Copyright © 2020 I-Connect007. All rights reserved.